Cliffview Sanitary Sewer – Proctorville, Ohio

This project entailed design of approximately 1,600 feet of 6-inch sanitary force main and a 1,500 GPM pump station. The purpose of the project was to eliminate a package treatment plant that was in the path of a proposed ODOT-funded state highway bypass project. The project was funded by cost-for-cure funds and included close coordination with ODOT, Lawrence County, and the existing package treatment plant owner/operator. Special design considerations included design of a restrained joint force main system that was capable of deflecting under the proposed road embankment due to an 18-inch estimated existing soil settlement. Careful consideration of pump station siting and force main routing was thoroughly conducted.

“Thanks so much for the friendly and professional service. Your speedy and thorough methods are making my building acquisition go very smoothly.”