Wastewater Treatment Replacement Construction Observation – ODNR – Deer Creek State Park, Mt. Sterling, Ohio

The Ohio Department of Natural Resources (ODNR) contracted STONE to provide periodic on-site construction observation during placement of a new on-site wastewater treatment system at Deer Creek State Park. STONE personnel observed the construction, plumbing, directional boring drilling, and electrical contractors and noted their progress on the project. Periodic documentation described the installation of the leach field, dosing tanks, and force main, as well as subsequent demolition of the old system. Maintenance of site conditions, such as clearing of disturbed areas, placement of silt fencing for erosion control, and final grading, were noted throughout the project and when satisfactorily completed.

“Having worked with STONE on a couple of projects I can say that Mary Sharrett and her staff work diligently to complete projects on time and in a highly professional manner.  They are trusted by state and federal agencies and their experience with permits saves the client time. They are among the best and I look forward to working with them again in the future.”