Construction Staking – Upper Arlington, Ohio

STONE was contracted to provide construction staking for new curb construction on 16 streets (about 43,000 linear feet) throughout this central Ohio municipality. Lath was spaced every 25 feet along curb alignments and at 10 to 15 foot spacing around corners. All were labeled with station and cut to curb elevation. Constant communication was maintained between STONE and the Contractor to ensure that staking was taking place ahead of work activities.

Related Projects

We have contracted STONE over the past 10 years to assist us with various environmental issues including environmental compliance audits, developments of our facility’s SPCC and SQPP plans, preparation of chemical inventory or Tier 2 reports, and other related environmental services. STONE always responds promptly and provides quality environmental service in a cost-effective manner.