MAD-42-24.75 US 42 Expansion – Construction Staking and Stormwater Pollution Protection Plan (SWP3) – Columbus, Ohio

STONE was contracted to review plans and provide Construction Staking for the contractor for this roadway widening project. Project responsibilities also included STONE’s CPESC-certified Engineers to prepare the Stormwater Pollution Prevention Plan (SWP3), noting that the project is located in the Big Darby Creek Watershed. As part of the SWP3, STONE’s accredited Certified Erosion, Sediment, & Storm Water Inspector (CESSWI) personnel conducted monthly inspections, noted areas that required corrective actions, and updated the SWP3 as needed.